ANNISTON– An Alabama Power transmission upgrade would involve 38.5 miles of existing line extending into Calhoun County, a federal document shows.
The U.S. Department of Energy’s Nov. 17 consultation letter describes the Gaston-to-Anniston project across Shelby, Talladega, and Calhoun counties. It connects a substation near the Gaston Steam Plant with the Bynum Transmission Substation.
Alabama Power plans work within an existing 100-foot-wide right-of-way. Construction is scheduled for Feb. 1, 2027, with commercial operation projected for December 2027.
The work also includes upgrading the 230-kilovolt line and replacing 15 structures. However, the listed structure replacements fall in Shelby and Talladega counties.
Historic-Preservation Review Underway
DOE seeks state historic-preservation officials’ agreement with its finding of no adverse effect on historic properties. The agency also contacted five federally recognized tribes for consultation.
However, the letter does not establish final financing approval for this project. Alabama Power has a federal loan guarantee covering multiple potential projects, but each requires individual review before financing approval.
Separately, DOE’s environmental notices page lists a Nov. 17–Dec. 17 consultation period. It directs comments to EDF_environmental@doe.gov, with “APC: Gaston to Anniston” in the subject line.